2012年项目管理认证练习题(中英文)10

2012-01-29 17:06:00 字体放大:  

6. The project Quality Management function does not include:

Quality policies, procedures, plans, specifications and requirements. And management reporting.

The technical process of establishing, the plan for monitoring and controlling project quality .

Technical quality control.

Managing the quality of the product.

项目质量管理的功能不包括:

质量方针、程序、计划、规格、要求和管理报告.

建立的技术过程、监测和控制项目质量的计划.

技术质量控制.

管理产品的质量.

7. Acceptance sampling is a necessary part of the typical manufacturing process and may be applied to many industries. Typically it is performed on incoming materials, on partially finished products at various intermediate stages of the manufacturing process, and on the final product. Acceptance sampling is very important because:

Companies do not have the time to perform 100% inspection due to schedule constraints.

100% inspection is impractical and uneconomical.

100% sampling causes inspector fatigue due to repetitive operations

b & c

可接受样本是典型制造工艺的必要部分同时可能应用在许多工业. 它典型的被用于进入的原料,部分的应用在完成产品的不同中间制造过程和最终产品. 可接受样本是非常重要的因为:

由于进度的限制公司没有时间执行100%的检测.

100%检测是不切实际的和不经济的.

100%取样由于重复操作导检查者疲乏

b和c

8. The four absolutes of quality are:

Definition, system, performance standard, and measurement.

Specs, target goal, uniformity of compliance and definition.

Cost of quality, zero defects, measurement, and system.

Specs, continuous inspection, rule of seven and cost of quality.

4个质量事件是:

定义,系统,执行标准和测量.

规格,目标,顺序一致和定义.

质量成本,零缺陷,测量和系统.

规格,持续检验,7个作用和质量成本

9. What percentage of poor quality is directly attributed to management?

65%

90%

45%

85%

百分之几引起质量缺陷的原因是由于管理层直接造成的 ?

65%

90%

45%

85%

10.The art of quality planning is:

Identifying which quality standards are relevant to the project and determine how to satisfy them.

Preparing the design to the customer’s specifications.

Monitoring the project results to decide if the outputs fulfill the requirements.

The overall intentions and direction of an organization in terms of quality.

质量计划的艺术是:

确认那一个质量标准同项目有关并决定如何满足它.

准备设计客户的规格.

检测项目结果决定其是否符合要求.

组织在质量上的意图和方向.